Office of the Secretary Manager
Kittitas Reclamation District Board of
Directors Meeting
August 8, 2017 Minutes
The Board of Directors of
the Kittitas Reclamation District (KRD) met in Regular Session on August 8, 2017
at 1:00 p.m. Attending the meeting were Division One Director and Chairman Mark
Hansen, Division Four Director and Vice Chairman Larry Bland, Division Three
Director Fred Schnebly, Division Two Director Ed Wakkuri, Division Five Director
Paul Weaver, Secretary Manager Urban Eberhart, Assistant Manager Kevin Eslinger,
Field Supervisor Bob Main, Treasurer Stacy Berg, Treasurer Barbara Pettit and
Lands Clerk & RRA Specialist Keli Bender. Legal Counsel Jeff Slothower attended
via teleconference. Also attending was land owner Janeice Jump.
The agenda was approved with
the addition of an executive session for reasons consistent with RCW
42.30.110(1)(b) and RCW 42.30.110(1)(i):(i). The motion was made by Director
Bland and the second was made by Director Weaver. The motion passed unanimously.
The minutes of the July 11,
2017 meeting were approved with a motion made by Director Bland and the second
made by Director Schnebly. The motion passed unanimously.
Water Update: Mr. Main
presented the current water supply information from the United States Bureau of
Reclamation (USBR). Presently the reservoirs are at 71% capacity overall which
is 110% of average. KRD is currently diverting 1,152 cfs. On August 8, 2017, the
recorded precipitation for the 2017 water year is 225.56 inches, 103% of
average. There has been no measurable precipitation so far in August. We are
expecting temperatures in the low to mid 80’s next week, and water orders are
beginning to decrease in demand as customers are cutting hay.
Summary Vouchers for the
June 2017 expenses and the July 2017 payroll which included check numbers 41325
through 41407 and direct deposit numbers 9901160 through 9901178 in the sum of
$486,971.44 were approved with a motion made by Director Weaver and the second
made by Director Schnebly. The motion passed unanimously. The Directors’ monthly
payroll vouchers were presented for signatures. Director Schnebly made a motion
to approve the vouchers, a second was made by Director Weaver. The motion passed
unanimously. The checks were distributed accordingly.
Maintenance Update: Mr. Main
reported that the crews are continuing to stock pile material for future
pipelines. The Freightliner Dump Truck is out of service after 3 injectors
stopped working. The vehicle is being repaired at this time. Crews continue to
keep up with the spraying and mowing. KRD began construction on the 6-inch steel
piping for the Tillman Creek Supplementation Project. A Department of Ecology
Grant is covering the cost of the piping. Preparation for the North Branch Phase
II Lining Project has begun. Work on the Taneum Bridge Project has started.
Public Comment: No public
comment.
Secretary Manager’s Activity
Report: An agreement has been made with Roza Irrigation District for the
purchase of a single axle dump truck. Director Weaver made a motion to approve
the purchase of the dump truck for $4,000.00, the second was made by Director
Bland. The motion passed unanimously.
Mr. Eberhart reported that
he participated in the KXLE AM talk show on August 1, 2017.
With the support of KRD
staff the first session of the John Keys Tour was successful. The participants
will be back again in October for the second session. KRD has been receiving
positive feedback from the attendees.
The furnace and air
conditioning unit had a complete failure and a new unit was purchased. KRD
obtained three bids from various businesses and Bid Mechanical provided the most
reasonable bid at $7,600.00. They were able to install the unit relatively
quickly and there have been no further issues since the installation. Director
Weaver made a motion to approve the purchase of the heating and cooling system,
and a second was made by Director Bland. The motion passed unanimously.
Mr. Eberhart continues to
work with the Marine Fisheries Advisory Committee Columbia Basin Partnership.
The group is focusing on recovery prototypes for the Mid-Columbia Steelhead as
well as four other fish species. One of the goals is to achieve Mid-Columbia
Steelhead delisting through efforts that include work through the Yakima Basin
Integrated Plan in the Upper Yakima Basin.
On June 28, 2017 KRD
received an email notice from the USBR Regional Office, authorizing KRD to
proceed on the North Branch Canal Lining Project Phase II Grant. The agreement
is still being written and is expected to be received by August 30, 2017. In the
agreement, it is anticipated that 1 Million dollars will be allocated for this
year. An additional 2 Million dollars should then be awarded. The Salmon
Recovery Funding Board has approved $290,000.00. Currently there should be
approximately 3.3 Million dollars available for construction this winter. KRD is
also working on a grant through the National Fish and Wildlife Foundation
(NFWF). If the state capital budget passes there would be an additional 2.1
Million dollars available to KRD. With the funds currently available KRD will
continue with the North Branch Lining Phase II Project. After prioritizing the
most important sections to line first it was determined that the next portion to
be lined would be from the pumping plant back up stream to, just short of the
tunnel. The additional 7000 feet of lining is estimated to cost $179,268.00 for
engineering services. Director Schnebly made a motion to approve the engineering
work and the second was made by Director Wakkuri. The motion passed unanimously.
The advertising will start the first week of September for the bidding process.
Jacobs Engineering has begun
the engineering portion of the Phase II South Branch Canal Lining Project.
The task agreement is
complete for the Easton Dam Drum Gate Carthodic Protection. Jacobs Engineering
will begin the work as soon as the water is shut off for the season.
The initial phase of the
Water Storage Assessment is complete. Next the sites will be narrowed down to
around three sites and it is hoped that construction will be possible within the
next five years. Jacobs is developing the scope of work for phase II of the
storage study.
Jacobs Engineering is
developing a plan for Phase I of the Pressure Tunnel work. A General Engineering
Support Task and a General Environmental Support Task with a limit of $25,000.00
each has been established. This allows KRD the ability to call Jacobs on a
particular issue without having to bid each process individually for general
items. Director Bland made a motion to approve the General Engineering Support
Task and General Environmental Support Task at $25,000.00 each, a second was
made by Director Schnebly. The motion passed unanimously.
Whiskey Creek- The City of
Ellensburg is moving forward with the purchase of some of the property. The
project is continuing with discussions that include the city, county, KRD and
others.
Kittitas County Conservation
District (KCCD), United States Bureau of Reclamation (USBR) and KRD continue
conversations on Manastash. Mr. Eberhart reported that an agreement is
continuing to be worked on and it is hoped that KRD will be participating in
2018.
KRD has scheduled the 2017
Tributary Supplementation Program Committee Meeting in August. The report will
be given and the committee will make recommendations to the USBR.
Manastash Ridge Trail has
nothing new to report.
Legal Counsel Slothower has
issued the first and second letters for the delinquent accounts and they have
been sent to the landowners. Treasurer Berg is working with Legal Counsel
Slothower to obtain the remaining funds. In September, a list will be provided
with the dollar amounts to determine whether the accounts are appropriate for
continuing collection action.
The Memorandum of
Understanding between KRD and Kittitas County is being developed. Assistant
Manager Eslinger and Treasurer’s Pettit and Berg met with Kittitas County
Treasurer Brett Wachsmith. Payments have been made to KRD on the property’s that
were previously sold. There are several properties that are pending, and
Kittitas County has agreed to pay KRD the assessments for those if the
properties are sold. The agreement will continue to be developed and then
presented to Kittitas County and KRD to be signed.
The Board adjourned to
Executive Session at 1:45 p.m. for 20 minutes per RCW 42.30.110(1)(b) and
42.30.110(1) (i):(i) with a motion made by Director Schnebly and a second made
by Director Bland. The motion passed unanimously. The executive session was
extended by 10 minutes. The Board returned to Regular Session at 2:15 p.m. with
a motion made by Director Weaver and the second was made by Director Bland. The
motion passed unanimously.
Other Business: Director
Weaver requested that Mr. Eberhart and Legal Counsel Slothower develop a
protocol to help Ditchrider’s and other employees to respond to difficult
situations.
All business having been
concluded the meeting was adjourned.
______________________________________
Mr. Hansen KRD Board of
Directors Chairman
______________________________________
Mr. Eberhart KRD Secretary
Manager