Office of the Secretary Manager
Kittitas Reclamation District Board of 
Directors Meeting
August 8, 2017 Minutes
The Board of Directors of 
the Kittitas Reclamation District (KRD) met in Regular Session on August 8, 2017 
at 1:00 p.m. Attending the meeting were Division One Director and Chairman Mark 
Hansen, Division Four Director and Vice Chairman Larry Bland, Division Three 
Director Fred Schnebly, Division Two Director Ed Wakkuri, Division Five Director 
Paul Weaver, Secretary Manager Urban Eberhart, Assistant Manager Kevin Eslinger, 
Field Supervisor Bob Main, Treasurer Stacy Berg, Treasurer Barbara Pettit and 
Lands Clerk & RRA Specialist Keli Bender. Legal Counsel Jeff Slothower attended 
via teleconference. Also attending was land owner Janeice Jump. 
The agenda was approved with 
the addition of an executive session for reasons consistent with RCW 
42.30.110(1)(b) and RCW 42.30.110(1)(i):(i). The motion was made by Director 
Bland and the second was made by Director Weaver. The motion passed unanimously.
The minutes of the July 11, 
2017 meeting were approved with a motion made by Director Bland and the second 
made by Director Schnebly. The motion passed unanimously.
Water Update: Mr. Main 
presented the current water supply information from the United States Bureau of 
Reclamation (USBR). Presently the reservoirs are at 71% capacity overall which 
is 110% of average. KRD is currently diverting 1,152 cfs. On August 8, 2017, the 
recorded precipitation for the 2017 water year is 225.56 inches, 103% of 
average. There has been no measurable precipitation so far in August. We are 
expecting temperatures in the low to mid 80’s next week, and water orders are 
beginning to decrease in demand as customers are cutting hay.
   
Summary Vouchers for the 
June 2017 expenses and the July 2017 payroll which included check numbers 41325 
through 41407 and direct deposit numbers 9901160 through 9901178 in the sum of 
$486,971.44 were approved with a motion made by Director Weaver and the second 
made by Director Schnebly. The motion passed unanimously. The Directors’ monthly 
payroll vouchers were presented for signatures. Director Schnebly made a motion 
to approve the vouchers, a second was made by Director Weaver. The motion passed 
unanimously. The checks were distributed accordingly.
Maintenance Update: Mr. Main 
reported that the crews are continuing to stock pile material for future 
pipelines. The Freightliner Dump Truck is out of service after 3 injectors 
stopped working. The vehicle is being repaired at this time. Crews continue to 
keep up with the spraying and mowing. KRD began construction on the 6-inch steel 
piping for the Tillman Creek Supplementation Project. A Department of Ecology 
Grant is covering the cost of the piping. Preparation for the North Branch Phase 
II Lining Project has begun. Work on the Taneum Bridge Project has started.
 
Public Comment: No public 
comment. 
Secretary Manager’s Activity 
Report: An agreement has been made with Roza Irrigation District for the 
purchase of a single axle dump truck. Director Weaver made a motion to approve 
the purchase of the dump truck for $4,000.00, the second was made by Director 
Bland. The motion passed unanimously. 
Mr. Eberhart reported that 
he participated in the KXLE AM talk show on August 1, 2017. 
With the support of KRD 
staff the first session of the John Keys Tour was successful. The participants 
will be back again in October for the second session. KRD has been receiving 
positive feedback from the attendees. 
The furnace and air 
conditioning unit had a complete failure and a new unit was purchased. KRD 
obtained three bids from various businesses and Bid Mechanical provided the most 
reasonable bid at $7,600.00. They were able to install the unit relatively 
quickly and there have been no further issues since the installation. Director 
Weaver made a motion to approve the purchase of the heating and cooling system, 
and a second was made by Director Bland. The motion passed unanimously. 
Mr. Eberhart continues to 
work with the Marine Fisheries Advisory Committee Columbia Basin Partnership. 
The group is focusing on recovery prototypes for the Mid-Columbia Steelhead as 
well as four other fish species. One of the goals is to achieve Mid-Columbia 
Steelhead delisting through efforts that include work through the Yakima Basin 
Integrated Plan in the Upper Yakima Basin. 
On June 28, 2017 KRD 
received an email notice from the USBR Regional Office, authorizing KRD to 
proceed on the North Branch Canal Lining Project Phase II Grant. The agreement 
is still being written and is expected to be received by August 30, 2017. In the 
agreement, it is anticipated that 1 Million dollars will be allocated for this 
year. An additional 2 Million dollars should then be awarded. The Salmon 
Recovery Funding Board has approved $290,000.00. Currently there should be 
approximately 3.3 Million dollars available for construction this winter. KRD is 
also working on a grant through the National Fish and Wildlife Foundation 
(NFWF). If the state capital budget passes there would be an additional 2.1 
Million dollars available to KRD. With the funds currently available KRD will 
continue with the North Branch Lining Phase II Project. After prioritizing the 
most important sections to line first it was determined that the next portion to 
be lined would be from the pumping plant back up stream to, just short of the 
tunnel. The additional 7000 feet of lining is estimated to cost $179,268.00 for 
engineering services. Director Schnebly made a motion to approve the engineering 
work and the second was made by Director Wakkuri. The motion passed unanimously. 
The advertising will start the first week of September for the bidding process. 
Jacobs Engineering has begun 
the engineering portion of the Phase II South Branch Canal Lining Project. 
The task agreement is 
complete for the Easton Dam Drum Gate Carthodic Protection. Jacobs Engineering 
will begin the work as soon as the water is shut off for the season. 
The initial phase of the 
Water Storage Assessment is complete. Next the sites will be narrowed down to 
around three sites and it is hoped that construction will be possible within the 
next five years. Jacobs is developing the scope of work for phase II of the 
storage study. 
Jacobs Engineering is 
developing a plan for Phase I of the Pressure Tunnel work. A General Engineering 
Support Task and a General Environmental Support Task with a limit of $25,000.00 
each has been established. This allows KRD the ability to call Jacobs on a 
particular issue without having to bid each process individually for general 
items. Director Bland made a motion to approve the General Engineering Support 
Task and General Environmental Support Task at $25,000.00 each, a second was 
made by Director Schnebly. The motion passed unanimously. 
Whiskey Creek- The City of 
Ellensburg is moving forward with the purchase of some of the property. The 
project is continuing with discussions that include the city, county, KRD and 
others. 
Kittitas County Conservation 
District (KCCD), United States Bureau of Reclamation (USBR) and KRD continue 
conversations on Manastash. Mr. Eberhart reported that an agreement is 
continuing to be worked on and it is hoped that KRD will be participating in 
2018. 
KRD has scheduled the 2017 
Tributary Supplementation Program Committee Meeting in August. The report will 
be given and the committee will make recommendations to the USBR. 
Manastash Ridge Trail has 
nothing new to report. 
Legal Counsel Slothower has 
issued the first and second letters for the delinquent accounts and they have 
been sent to the landowners. Treasurer Berg is working with Legal Counsel 
Slothower to obtain the remaining funds. In September, a list will be provided 
with the dollar amounts to determine whether the accounts are appropriate for 
continuing collection action.  
The Memorandum of 
Understanding between KRD and Kittitas County is being developed. Assistant 
Manager Eslinger and Treasurer’s Pettit and Berg met with Kittitas County 
Treasurer Brett Wachsmith. Payments have been made to KRD on the property’s that 
were previously sold. There are several properties that are pending, and 
Kittitas County has agreed to pay KRD the assessments for those if the 
properties are sold. The agreement will continue to be developed and then 
presented to Kittitas County and KRD to be signed. 
The Board adjourned to 
Executive Session at 1:45 p.m. for 20 minutes per RCW 42.30.110(1)(b) and 
42.30.110(1) (i):(i) with a motion made by Director Schnebly and a second made 
by Director Bland. The motion passed unanimously. The executive session was 
extended by 10 minutes. The Board returned to Regular Session at 2:15 p.m. with 
a motion made by Director Weaver and the second was made by Director Bland. The 
motion passed unanimously.
Other Business: Director 
Weaver requested that Mr. Eberhart and Legal Counsel Slothower develop a 
protocol to help Ditchrider’s and other employees to respond to difficult 
situations.   
All business having been 
concluded the meeting was adjourned.
______________________________________
Mr. Hansen KRD Board of 
Directors Chairman
______________________________________
Mr. Eberhart KRD Secretary 
Manager